Edison Park - Nashville “The Nations”

At Edison Park in Nashville, TN, Trinity Earthworks completed all grading and excavation associated with the construction of five bio-retention ponds designed for effective stormwater management. Scope included precise excavation to engineered depths and contours, as well as grading to ensure proper drainage flow and long-term functionality of each pond.

The project involved the removal and haul-off of approximately 4,000 tons of material, requiring careful coordination of trucking, site access, and sequencing to maintain efficiency and schedule. Our team worked closely with site plans and environmental requirements to ensure each pond met design specifications and compliance standards.

From initial excavation through final grading, the work was executed with a focus on accuracy, erosion control, and sustainability—delivering a critical component of the site’s overall stormwater system.